CIL and Section 106, explained

Planning obligations are real cash, and on some sites they're the reason a deal doesn't work. Here's what the Community Infrastructure Levy and Section 106 agreements are, how they differ, and how to allow for them properly in an appraisal.

Ask two developers about "planning contributions" and you'll often get two different answers, because there are two different mechanisms at work — CIL and Section 106. They're calculated differently, spent differently, and negotiated differently. Getting them right in an appraisal matters, because they come straight off your bottom line.

Two different things, often confused

Both are ways the planning system captures a contribution from development toward its impacts, but they work in opposite ways:

Not every council charges CIL, but most operate S106. Many schemes face both. The two are meant to be complementary — CIL for general infrastructure, S106 for site-specific mitigation and affordable housing.

The Community Infrastructure Levy (CIL)

CIL is a charge, set locally, that funds the broad infrastructure needed to support growth — schools, roads, open space, health facilities. Each charging authority publishes a charging schedule with rates (in £ per m²) that can vary by location within the area and by type of development. It's deliberately simple and certain: you can look up the rate and calculate the liability yourself before you even apply.

How CIL is calculated

The core of the CIL calculation is straightforward:

The formula, in essence

CIL liability ≈ the council's rate (£/m²) × the net additional internal floorspace you're creating (m²) × an indexation figure that adjusts the rate for construction-cost inflation since the schedule was set.

Two things matter here. First, it's net additional floorspace — existing lawful floorspace being demolished or reused can, in defined circumstances, be offset, which is why a knock-down-and-rebuild can carry far less CIL than a bare-site scheme of the same size. Second, the indexation means the headline rate on an old charging schedule isn't the rate you actually pay — the real figure has been inflated to current costs.

Illustrative CIL calculation
New internal floorspace created750 m²
Less existing floorspace offset (demolished)(150 m²)
Net chargeable floorspace600 m²
Council rate (illustrative)£110/m²
× indexation (illustrative)× 1.25
Indicative CIL liability£82,500

Always confirm the actual rate, indexation and any offset against the specific council's current charging schedule — these figures are illustrative only.

Section 106 agreements

A Section 106 agreement (a "planning obligation") is a legal contract between the developer and the local authority, tied to a planning permission. Unlike CIL, it's negotiated and site-specific. Typical obligations include:

Because it's negotiated, S106 is where there's room for discussion — including, crucially, on viability. If the obligations sought would make a scheme unviable, that can be evidenced and negotiated, which is one reason a rigorous appraisal is a developer's most useful document in a planning conversation.

Affordable housing

On schemes above a threshold (often around 10 units, though it varies), local policy typically requires a proportion of the homes to be affordable — sometimes a substantial share. Affordable housing is usually delivered on-site and sold to a registered provider at well below open-market value, or occasionally as a commuted financial sum. In an appraisal this shows up as reduced GDV on those units, and it can be the single biggest planning cost on a scheme — far larger than CIL — so it must be modelled explicitly rather than lumped into a percentage.

Exemptions and reliefs

Several reliefs and exemptions exist, and they can materially change the numbers. Commonly relevant ones include self-build exemption (for those building their own home), relief for certain small extensions and annexes, and offsets for existing floorspace. There are also minimum thresholds below which CIL may not apply. These are rule-bound and time-sensitive — claimed through the correct forms at the right stage — so treat them as something to confirm with the authority, not assume.

What about the Infrastructure Levy?

You may have read that CIL and S106 are being replaced by a single "Infrastructure Levy," proposed under the Levelling-up and Regeneration Act 2023. In practice, its introduction has been delayed substantially — reported to be pushed back by up to a decade — so for any scheme you're appraising now, CIL and Section 106 remain the live system. Keep an eye on it, but plan and appraise around the rules as they stand today.

How to allow for them in an appraisal

Planning obligations belong in an appraisal as explicit, evidenced lines — not a vague percentage:

On a marginal site, these are often the difference between a deal and a pass — which is exactly why they belong in the screening stage, not discovered late.

Factor obligations in before you commit.

Model CIL, affordable housing and Section 106 as real lines in your appraisal — and see whether the deal still stacks once they're in.

Common questions

What is the difference between CIL and Section 106?

CIL (the Community Infrastructure Levy) is a fixed, non-negotiable charge set by a local formula — a rate per square metre of new floorspace — used for general infrastructure. Section 106 is a negotiated, site-specific legal agreement covering things like affordable housing and contributions to mitigate a scheme's particular impacts. Many developments face both.

How is CIL calculated?

Broadly, the council's rate in pounds per square metre is multiplied by the net additional internal floorspace being created, then adjusted by an indexation figure for construction-cost inflation since the charging schedule was set. Existing lawful floorspace being demolished or reused can sometimes be offset against the chargeable area.

What does a Section 106 agreement cover?

Site-specific planning obligations — most importantly affordable housing, plus financial contributions toward local infrastructure the scheme affects (education, transport, open space, healthcare) and any required on-site works or restrictions. Because it's negotiated, S106 can be discussed on viability grounds.

Are there exemptions from CIL?

Yes. Common reliefs include self-build exemption for people building their own home, relief for certain extensions and annexes, offsets for existing floorspace, and minimum thresholds below which CIL may not apply. Reliefs are rule-bound and must be claimed correctly and at the right stage, so confirm eligibility with the charging authority.

Is the Infrastructure Levy replacing CIL and Section 106?

It was proposed to, under the Levelling-up and Regeneration Act 2023, but its introduction has been delayed substantially — reported to be by up to a decade. For schemes being appraised now, CIL and Section 106 remain the system in force, so plan and appraise around today's rules.

Residual is decision-support for development appraisal, not a RICS Red Book valuation and not financial, tax or planning advice. Any figures are illustrative and vary by site, specification and location. Sales values and land price are always your own inputs. For formal valuation, planning or tax advice, consult a qualified professional.